Works to bring Metrobus to Av. Mário Brito in 2026

Work in Perafita starts on 10 September and is expected to last six months
The work on Avenida Mário Brito is part of the Design and Construction project for the Matosinhos MetroBus / BRT Line, a key mobility project for the municipality. The new line, approximately 10 kilometres long with 11 stations, will connect Francisco Sá Carneiro Airport, Perafita, Leça da Palmeira and Matosinhos, using 100% electric vehicles and with an estimated 17,500 journeys per day.
The project will strengthen public transport provision, improve connections between different areas of the municipality and contribute to more sustainable mobility by reducing car traffic and carbon emissions.